01_Test Agile – Agile Principles and Mindset
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 01_Test Agile - Agile Principles and Mindset
Mulțumim pentru participarea la testul 01_Test Agile - Agile Principles and Mindset. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Which of the following is NOT an advantage of limiting work in progress?
Correct
Congratulations!
Incorrect
The correct answer is D. It maximizes resource utilization to make processes work more efficiently.
-
Question 2 of 20
2. Question
The relationship between leadership and management in agile methods is:
Correct
Congratulations!
Incorrect
The correct answer is C. Management and leadership are used together.
-
Question 3 of 20
3. Question
The core values of XP include:
Correct
Congratulations!
Incorrect
The correct answer is C. Feedback, simplicity, communication
-
Question 4 of 20
4. Question
In the Agile Manifesto, what is valued more than processes and tools?
Correct
Congratulations!
Incorrect
The correct answer is B. Individuals and interactions
-
Question 5 of 20
5. Question
The acronym WIP stands for:
Correct
Congratulations!
Incorrect
The correct answer is B. Work in progress
-
Question 6 of 20
6. Question
The three pillars of Scrum are:
Correct
Congratulations!
Incorrect
The correct answer is D. Transparency, Inspection, Adaptation
-
Question 7 of 20
7. Question
On a typical agile team, who has the best insight into task execution?
Correct
Congratulations!
Incorrect
The correct answer is B. Team members
-
Question 8 of 20
8. Question
Which of the following Agile Manifesto values deals most closely with WIP?
Correct
Congratulations!
Incorrect
The correct answer is C. Working software over comprehensive documentation
-
Question 9 of 20
9. Question
What in one of the three questions that are addresses in the daily scrum?
Correct
Congratulations!
Incorrect
The correct answer is A. What have I done since the last daily scrum?
-
Question 10 of 20
10. Question
What are three of the seven lean core concepts?
Correct
Congratulations!
Incorrect
The correct answer is C. Optimize the whole, defer decisions, amplify learning
-
Question 11 of 20
11. Question
The four primary roles of a servant leader include:
Correct
Congratulations!
Incorrect
The correct answer is A. Shielding the team members from interruptions
-
Question 12 of 20
12. Question
In Scrum, the definition of the done is created with the input of everyone except the:
Correct
Congratulations!
Incorrect
The correct answer is D. Process owner
-
Question 13 of 20
13. Question
In the lean approach, which of the following wouldn’t be considered an example of one of the seven forms of waste?
Correct
Congratulations!
Incorrect
The correct answer is B. Testing the code
-
Question 14 of 20
14. Question
The XP core practices include:
Correct
Congratulations!
Incorrect
The correct answer is A. Whole team, planning games, small releases
-
Question 15 of 20
15. Question
Which of the following is one of the planned opportunities for inspection and adaptation in the Scrum method?
Correct
Congratulations!
Incorrect
The correct answer is C. Daily scrum
-
Question 16 of 20
16. Question
Which of the following is an Agile Manifesto value?
Correct
Congratulations!
Incorrect
The correct answer is D. Customer collaboration over contract negotiation
-
Question 17 of 20
17. Question
The agile triangle of constraints is said to be inverted from the traditional triangle because it allows:
Correct
Congratulations!
Incorrect
The correct answer is D. Scope to vary while time and cost are fixed
-
Question 18 of 20
18. Question
Which of the following Agile Manifesto principles reflects the agile focus on team empowerment?
Correct
Congratulations!
Incorrect
The correct answer is D. Build projects around motivated individuals.
-
Question 19 of 20
19. Question
The Kanban pull system means that:
Correct
Congratulations!
Incorrect
The correct answer is B. Each time a work item is completed, the next work item is “pulled” into that stage of the process.
-
Question 20 of 20
20. Question
Which of the following isn’t a core aspect of the agile mindset?
Correct
Congratulations!
Incorrect
The correct answer is C. Respect the process
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
02_Test Agile – Value – Driven Delivery
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 02_Test Agile - Value - Driven Delivery
Mulțumim pentru participarea la testul 02_Test Agile - Value - Driven Delivery. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Which of the following is not a form of frequent verification and validation?
Correct
Congratulations!
Incorrect
The correct answer is D. Iteration planning
-
Question 2 of 20
2. Question
Which set of tools is least likely to be used by an agile team?
Correct
Congratulations!
Incorrect
The correct answer is C. Scheduling software, Gantt charts
-
Question 3 of 20
3. Question
A sponsor wants to evaluate a proposed three-year project against two proposed one-year projects.
Correct
Congratulations!
Incorrect
The correct answer is A. NPV
-
Question 4 of 20
4. Question
The purpose of continuous integration is to:
Correct
Congratulations!
Incorrect
The correct answer is D. Find code issues as soon as possible
-
Question 5 of 20
5. Question
Which of the following is NOT a recognized agile prioritization scheme?
Correct
Congratulations!
Incorrect
The correct answer is C. Prioritization based on iteration velocity
-
Question 6 of 20
6. Question
Which of the following is true about agile contracts?
Correct
Congratulations!
Incorrect
The correct answer is C. They need to be able to accommodate changes.
-
Question 7 of 20
7. Question
You are working on a software development team that follows a test-driven development process. The sequence of activities you would undertake is:
Correct
Congratulations!
Incorrect
The correct answer is C. Write test, write code, refactor
-
Question 8 of 20
8. Question
Which of the following is most likely to be an MVP?
Correct
Congratulations!
Incorrect
The correct answer is D. A chair that has no back
-
Question 9 of 20
9. Question
The sponsor is trying to determine which project has the greatest business value – one that returns $4 million in three years or one that returns $5 million in four years. The interest rate is 5 percent for borrowing capital to develop the projects. The best approach to determine the highest-value project is:
Correct
Congratulations!
Incorrect
The correct answer is C. Calculate the NPV of the projects, and choose the project with the highest value.
-
Question 10 of 20
10. Question
You have been asked to outline the nasics of agile contracting for your steering committee. Which of the following statements best describes the recommended approach to contracting on agile projects?
Correct
Congratulations!
Incorrect
The correct answer is D. The contract is worded to allow for reprioritization of scope, and acceptance is based on items being fit for business purpose.
-
Question 11 of 20
11. Question
MoSCoW and dot voting are forms of:
Correct
Congratulations!
Incorrect
The correct answer is C. Prioritization
-
Question 12 of 20
12. Question
What is the primary benefit of involving business representatives in the prioritization of work?
Correct
Congratulations!
Incorrect
The correct answer is D. To better understand the business needs for the project
-
Question 13 of 20
13. Question
Which of the following is not a valid agile KPI?
Correct
Congratulations!
Incorrect
The correct answer is C. Rate of velocity
-
Question 14 of 20
14. Question
Project X has an IRR of 12 percent, and project Y has an IRR of 10 percent. Which project represents the better rate of return?
Correct
Congratulations!
Incorrect
The correct answer is C. Project X
-
Question 15 of 20
15. Question
Which of the statements below best describes the agile concept of incremental delivery?
Correct
Congratulations!
Incorrect
The correct answer is B. The product is built and evaluated in chunks that, by the end of the project, comprise the complete product, including agreed-upon change requests that arose during the process.
-
Question 16 of 20
16. Question
In software development, the process of frequently integrating new and changed code into the project code repository is known as:
Correct
Congratulations!
Incorrect
The correct answer is B. Continuos integration
-
Question 17 of 20
17. Question
Little’s Law demonstrates that:
Correct
Congratulations!
Incorrect
The correct answer is A. The duration of a work queue is dependent on its size.
-
Question 18 of 20
18. Question
How is risk related to value delivery?
Correct
Congratulations!
Incorrect
The correct answer is D. Risk is anti-value.
-
Question 19 of 20
19. Question
The shorthand summary for the test-driven development sequence is:
Correct
Congratulations!
Incorrect
The correct answer is B. Red, Green, Refactor
-
Question 20 of 20
20. Question
What is an S-curve?
Correct
Congratulations!
Incorrect
The correct answer is A. A graph that tracks costs or some other variable over time
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
03_Test Agile – Stakeholder Engagement
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 03_Test Agile - Stakeholder Engagement
Mulțumim pentru participarea la testul 03_Test Agile - Stakeholder Engagement. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Which of the following statements best describes the role of an agile project manager?
Correct
Congratulations!
Incorrect
The correct answer is C. Defines the who, what, where, when, why, and how of the project and provides authority to proceed.
-
Question 2 of 20
2. Question
Agile’s emphasis on two-way communication means that:
Correct
Congratulations!
Incorrect
The correct answer is C. The customer should solicit the delivery team’s ideas, risks, and concerns and take them seriously.
-
Question 3 of 20
3. Question
Which of the following statements about the quadrants of emotional intelligence is correct?
Correct
Congratulations!
Incorrect
The correct answer is D. Social awareness deals with empathy.
-
Question 4 of 20
4. Question
Which of the following is a brainstorming technique?
Correct
Congratulations!
Incorrect
The correct answer is A. Quiet writing
-
Question 5 of 20
5. Question
Agile knowledge sharing is designed to:
Correct
Congratulations!
Incorrect
The correct answer is A. Make information available to anyone who might be interested
-
Question 6 of 20
6. Question
Which of the following pieces of information are we least likely to find in an agile charter?
Correct
Congratulations!
Incorrect
The correct answer is D. A precise cost or time estimate for the project
-
Question 7 of 20
7. Question
Which of the circumstances outlined below would be a good fit for the use of personas?
Correct
Congratulations!
Incorrect
The correct answer is B. When we are trying to better understand stakeholder demographics and needs
-
Question 8 of 20
8. Question
When comparing communication media, which of the following is true?
Correct
Congratulations!
Incorrect
The correct answer is D. Face-to-face communication has the highest effectiveness and the highest richness.
-
Question 9 of 20
9. Question
Your project team is in turmoil, and you’re trying to diagnose the level of their conflict with another department. You notice that statements such as “Marketing has no clue again!” are becoming commonplace. What level of conflict would you say the team is experiencing?
Correct
Congratulations!
Incorrect
The correct answer is C. Level 3
-
Question 10 of 20
10. Question
High-visibility displays of project information are called:
Correct
Congratulations!
Incorrect
The correct answer is C. Information radiators
-
Question 11 of 20
11. Question
Which of the following isn’t a form of agile workshop?
Correct
Congratulations!
Incorrect
The correct answer is D. The team gathers to share their progress yesterday, discuss what they will do today, and identify any impediments to progress.
-
Question 12 of 20
12. Question
What isn’t part of emotional intelligence?
Correct
Congratulations!
Incorrect
The correct answer is D. The ability to control other people’s emotions
-
Question 13 of 20
13. Question
The concept of knowledge sharing on an agile project is best characterized as:
Correct
Congratulations!
Incorrect
The correct answer is B. Central to many agile practices
-
Question 14 of 20
14. Question
Wireframe models help agile teams:
Correct
Congratulations!
Incorrect
The correct answer is B. Confirm designs
-
Question 15 of 20
15. Question
The gulf of evaluation refers to what?
Correct
Congratulations!
Incorrect
The correct answer is B. The mismatch between the customer’s vision of the solution and how the developers understand it
-
Question 16 of 20
16. Question
On an agile project, the definition of done is discussed frequently so that:
Correct
Congratulations!
Incorrect
The correct answer is B. All stakeholders have a clear understanding of what completion means.
-
Question 17 of 20
17. Question
Agile modeling aims to:
Correct
Congratulations!
Incorrect
The correct answer is A. Capture the intent of the design in a barely sufficient way.
-
Question 18 of 20
18. Question
Your team seems to unproductively debate even trivial decisions. To help them make collective decisions, you could try using:
Correct
Congratulations!
Incorrect
The correct answer is A. Fist-of-five voting
-
Question 19 of 20
19. Question
Which of the circumstances outlined below would be a good fit for the use of wireframes?
Correct
Congratulations!
Incorrect
The correct answer is A. When the conversation is centered on the high-level flow of a process
-
Question 20 of 20
20. Question
Which of the following benefits isn’t part of the agile value proposition?
Correct
Congratulations!
Incorrect
The correct answer is A. Reduced risk at the end of the project.
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
04_Test Agile – Team Performance
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 04_Test Agile - Team Performance
Mulțumim pentru participarea la testul 04_Test Agile - Team Performance . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
At what team formation and development phase is conflict likely to be highest?
Correct
Congratulations!
Incorrect
The correct answer C. Storming
-
Question 2 of 20
2. Question
Which of the following statements is true for using team velocity as progress metric?
Correct
Congratulations!
Incorrect
The correct answer is D. Velocity measurements account for work done and disruptions on the project.
-
Question 3 of 20
3. Question
Which of the following needs isn’t relevant to designing agile team spaces?
Correct
Congratulations!
Incorrect
The correct answer is B. Help everyone understand how to operate and reset the printer.
-
Question 4 of 20
4. Question
Self-organizing teams are best characterized by their ability to:
Correct
Congratulations!
Incorrect
The correct answer is C. Make local decisions
-
Question 5 of 20
5. Question
You have been assigned to lead a distributed agile team. To help communicate, the best opinion would be to:
Correct
Congratulations!
Incorrect
The correct answer is C. Set up some initial face-to-face meetings for everyone to meet each other.
-
Question 6 of 20
6. Question
The observation that an experienced driver can successfully navigate a winding mountain road while thinking about dinner is explained by which of the models we’ve discussed?
Correct
Congratulations!
Incorrect
The correct answer is A. Dreyfus model of skill acquisition
-
Question 7 of 20
7. Question
What variables does a typical burndown chart display on each axis?
Correct
Congratulations!
Incorrect
The correct answer is C. X-axis = time; Y-axis = estimated effort remaining
-
Question 8 of 20
8. Question
What is the term for the undocumented information collectively shared by co-located teams?
Correct
Congratulations!
Incorrect
The correct answer is C. Tacit knowledge
-
Question 9 of 20
9. Question
Tuckman’s stages of team formation and development follow what sequence?
Correct
Congratulations!
Incorrect
The correct answer is D. Forming, Storming, Norming, Performing
-
Question 10 of 20
10. Question
Agile team members are most effective at solving problems when they:
Correct
Congratulations!
Incorrect
The correct answer is C. Feel they have permission to make mistakes
-
Question 11 of 20
11. Question
Which of the following is not a recommendation for one-on-one coaching?
Correct
Congratulations!
Incorrect
The correct answer is D. Let the team resolve conflicts.
-
Question 12 of 20
12. Question
Cokcburn’s Shu-Ha-Ri model tells us why:
Correct
Congratulations!
Incorrect
The correct answer is D. Teams new to agile should follow a method that has already been tested by others.
-
Question 13 of 20
13. Question
High-performing agile teams feature which of the following sets of characteristics?
Correct
Congratulations!
Incorrect
The correct answer is D. Constructive disagreement, empowered, self-organizing
-
Question 14 of 20
14. Question
Making sure the team’s agile practices are working well and helping the team fulfill their agile roles is an example of:
Correct
Congratulations!
Incorrect
The correct answer is A. Coaching
-
Question 15 of 20
15. Question
Which of the following statements is false for distributed teams?
Correct
Congratulations!
Incorrect
The correct answer is B. They should have an easier Storming phase.
-
Question 16 of 20
16. Question
Another agile team leader in your organization comes to you for advice. She’s having trouble getting her team to take ownership of the project and get comfortable selecting the work to be done. She keeps finding herself making the decisions and directing the work. What do you advise her to do?
Correct
Congratulations!
Incorrect
The correct answer is C. Meet them halfway and work with their functional managers to align each team member’s goals with the project goals.
-
Question 17 of 20
17. Question
Which stage of team development calls for the Coaching style of leadership, which involves a high degree of both supportive and directing behavior from the leader?
Correct
Congratulations!
Incorrect
The correct answer is B. Storming
-
Question 18 of 20
18. Question
Blanchard and Hersey’s situational leadership stages, in sequence, are:
Correct
Congratulations!
Incorrect
The correct answer is D. Directing, Coaching, Supporting, Delegating
-
Question 19 of 20
19. Question
The primary reason constructive disagreement is valued on high-performing agile teams is to:
Correct
Congratulations!
Incorrect
The correct answer is C. Generate buy-in for decisions.
-
Question 20 of 20
20. Question
Osmotic communication works best when:
Correct
Congratulations!
Incorrect
The correct answer is D. The team members work near each other.
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
05_Test Agile – Adaptive Planning
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 05_Test Agile - Adaptive Planning
Mulțumim pentru participarea la testul 05_Test Agile - Adaptive Planning. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Your sponsor has asked for clarification on when releases of your product will ship and what those releases will contain. Which agile deliverables would best address this need?
Correct
Congratulations!
Incorrect
The correct answer is B. Product roadmap
-
Question 2 of 20
2. Question
What is product roadmap?
Correct
Congratulations!
Incorrect
The correct answer is B. A diaphragm of release plans
-
Question 3 of 20
3. Question
Which of the following is a valid requirements hierarchy progressing from large to small?
Correct
Congratulations!
Incorrect
The correct answer is B. Feature, user story, task
-
Question 4 of 20
4. Question
What is velocity not used for?
Correct
Congratulations!
Incorrect
The correct answer is D. Defining feature requirements
-
Question 5 of 20
5. Question
The INVEST mnemonic reminds us that stories should be:
Correct
Congratulations!
Incorrect
The correct answer is C. Negotiable, estimable, small
-
Question 6 of 20
6. Question
The most common user story format includes which of the following elements?
Correct
Congratulations!
Incorrect
The correct answer is A. Role, functionality, benefit
-
Question 7 of 20
7. Question
“Fast failure” means:
Correct
Congratulations!
Incorrect
The correct answer is A. Finding a fatal design flaw early in a project
-
Question 8 of 20
8. Question
A short timeboxed period set aside to investigate and eliminate a risk is called a:
Correct
Congratulations!
Incorrect
The correct answer is C. Risk-based spike
-
Question 9 of 20
9. Question
The three questions that are answered in daily stand-up meetings aim to:
Correct
Congratulations!
Incorrect
The correct answer is A. Identify problems and describe accomplishments.
-
Question 10 of 20
10. Question
Your team committed to delivering 10 story points this iteration, but it looks like you will only complete 8. You should:
Correct
Congratulations!
Incorrect
The correct answer is C. Complete 8 points, and put 2 back in the backlog.
-
Question 11 of 20
11. Question
When agile teams use the term “timeboxed”, what do they mean?
Correct
Congratulations!
Incorrect
The correct answer is B. Work can take no more than a maximum amount of time.
-
Question 12 of 20
12. Question
The project management office is auditing your agile project and asks to see your iteration plans. They notice that only the next couple of iterations have plans. As a result, they give the project a “red flag” for having incomplete plans. The most responsible thing to do is:
Correct
Congratulations!
Incorrect
The correct answer is A. Explain the agile principles of progressive elaboration and rolling wave planning.
-
Question 13 of 20
13. Question
Which of the following statements correctly describes agile planning?
Correct
Congratulations!
Incorrect
The correct answer is C. Plan at multiple levels, and have team members create iteration plans.
-
Question 14 of 20
14. Question
When conducting an iteration-planning using a Scrum-based approach, which of the following statements is not true?
Correct
Congratulations!
Incorrect
The correct answer is D. The Scrum Master selects the topic items off the backlog
-
Question 15 of 20
15. Question
You are leading a team with an average of 50 points per iteration. Another team of the same size in your organization is working on a project with similar complexity. The other team’s velocity is averaging 75 points per month. Your team should:
Correct
Congratulations!
Incorrect
The correct answer is C. Ignore the difference.
-
Question 16 of 20
16. Question
Estimates should be present as ranges to:
Correct
Congratulations!
Incorrect
The correct answer is D. Reflect the level of uncertainty in the estimates.
-
Question 17 of 20
17. Question
Your team is average 40 story points per two-week iteration. They have 200 points’ worth of functionality left in the user story backlog. How many weeks can we expect it will take until development is completed?
Correct
Congratulations!
Incorrect
The correct answer is C. 10
-
Question 18 of 20
18. Question
When using story points to estimate a project, which of the following statements is most accurate?
Correct
Congratulations!
Incorrect
The correct answer is A. The team owns the definition of what constitutes a story point.
-
Question 19 of 20
19. Question
Affinity estimating allows a team to:
Correct
Congratulations!
Incorrect
The correct answer is B. Confirm that stories that have been estimated as the same size are of equivalent magnitude.
-
Question 20 of 20
20. Question
You are a full time Scrum Master on an agile team. A team member becomes ill partway through an iteration in which the team committed to deliver 25 story points. Which action is most appropriate?
Correct
Congratulations!
Incorrect
The correct answer is D. Deliver what you can within the sprint.
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
06_Test Agile – Problem Detecting and Resolution
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 06_Test Agile - Problem Detecting and Resolution
Mulțumim pentru participarea la testul 06_Test Agile - Problem Detecting and Resolution. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Which of the following isn’t characteristic of the agile approach to problem solving?
Correct
Congratulations!
Incorrect
The correct answer is B. Iterative and incremental
-
Question 2 of 20
2. Question
We put risk mitigation stories in the backlog to:
Correct
Congratulations!
Incorrect
The correct answer is C. Ensure that risk reduction efforts are done in the early iterations.
-
Question 3 of 20
3. Question
Which scenario is an example of treating a change as coming from common causes of variation, when it actually comes from a special cause?
Correct
Congratulations!
Incorrect
The correct answer is D. Assuring the sponsor that the team will finish the release on time next month based on their historical average velocity, even though the senior developer just broke her leg and will be out for six weeks
-
Question 4 of 20
4. Question
What are the primary criteria used for prioritizing the stories in the backlog?
Correct
Congratulations!
Incorrect
The correct answer is C. Business value and risk reduction
-
Question 5 of 20
5. Question
As the team lead, you have been asked to explain to the business what the project team has accomplished during Iteration 0. Which of the following tools would you use for this presentation?
Correct
Congratulations!
Incorrect
The correct answer is B. Risk burndown graph
-
Question 6 of 20
6. Question
Which activity wouldn’t help us find issues earlier on the cost of change curve?
Correct
Congratulations!
Incorrect
The correct answer is C. Velocity
-
Question 7 of 20
7. Question
As the team’s agile coach, you measure small amounts of variance in task duration. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is D. Accept some variance as inevitable.
-
Question 8 of 20
8. Question
What is not one of the success strategies identified by Cockburn?
Correct
Congratulations!
Incorrect
The correct answer is C. Invent rather than research.
-
Question 9 of 20
9. Question
The errors that are missed by quality assurance and quality control and make it into production are called:
Correct
Congratulations!
Incorrect
The correct answer is C. Escaped defects
-
Question 10 of 20
10. Question
What is the advantage of using risk severity instead of expected monetary value (EMV) to rank risks?
Correct
Congratulations!
Incorrect
The correct answer is A. Risk severity helps us focus on the relative value of the risk.
-
Question 11 of 20
11. Question
Trends are useful because they are what type of indicator?
Correct
Congratulations!
Incorrect
The correct answer is B. Leading metrics
-
Question 12 of 20
12. Question
What is one cause of technical debt?
Correct
Congratulations!
Incorrect
The correct answer is B. Refactoring that hasn’t been done on a regular basis
-
Question 13 of 20
13. Question
Control limits can be described as:
Correct
Congratulations!
Incorrect
The correct answer is A. Process controls that define acceptable ranges of variation
-
Question 14 of 20
14. Question
On agile projects, the term “cycle time” usually refers to:
Correct
Congratulations!
Incorrect
The correct answer is B. The time required for the team to complete a work item, from start to finish
-
Question 15 of 20
15. Question
On a risk burndown graph, ideally we want to see:
Correct
Congratulations!
Incorrect
The correct answer is B. All the lines going down, as close to zero as possible, as soon as possible
-
Question 16 of 20
16. Question
What is the agile approach to problem solving?
Correct
Congratulations!
Incorrect
The correct answer is C. When a problem arises, either fix it on the spot or add it to the backlog
-
Question 17 of 20
17. Question
As a team member, if you encounter a tricky problem during a development iteration, agile recommends that you:
Correct
Congratulations!
Incorrect
The correct answer is D. Quickly bring the problem to your team members and ask for their help in solving it, since many heads are better than one.
-
Question 18 of 20
18. Question
Stories and features are prioritized in the risk-adjusted backlog based on their:
Correct
Congratulations!
Incorrect
The correct answer is C. Expected monetary value or business value
-
Question 19 of 20
19. Question
When a problem arises, what steps are needed?
Correct
Congratulations!
Incorrect
The correct answer is C. Diagnose the problem, decide what to do about it, and fix the problem (remove the bad work and redo it).
-
Question 20 of 20
20. Question
What is the least likely reason why changes found later in the project are more costly to fix?
Correct
Congratulations!
Incorrect
The correct answer is D. More features might have to be supported.
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
07_Test Agile – Continuous Improvement
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 07_Test Agile - Continuous Improvement
Mulțumim pentru participarea la testul 07_Test Agile - Continuous Improvement. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
In the first part of a retrospective, a team has identified a number of problems. What sequence of steps should they follow to explore and solve those problems?
Correct
Congratulations!
Incorrect
The correct answer is B. Gather data, generate insights, decide what to do
-
Question 2 of 20
2. Question
Your team spends 10 minutes waiting for people to turn up for the daily stand-up meeting, which then last 15 minutes. The stand-up meeting is then followed by another 5 minutes of the team discussing the hockey game last night, and yet another 5 minutes brainstorming issues to solve. Calculate the total cycle time of this process, assuming that the hockey discussion is not categorized as a value-added activity
Correct
Congratulations!
Incorrect
The correct answer is D. 35 minutes
-
Question 3 of 20
3. Question
When generating insights in a retrospective, we ask ”why” five times to:
Correct
Congratulations!
Incorrect
The correct answer is A. Move beyond our automatic, habitual answers and get to the root cause of an issue.
-
Question 4 of 20
4. Question
Which of the following is a form of agile review?
Correct
Congratulations!
Incorrect
The correct answer is B. Customer demos
-
Question 5 of 20
5. Question
What are some of the techniques a team can use to decide what to do about the issues they’ve identified in a retrospective?
Correct
Congratulations!
Incorrect
The correct answer is C. Short Subjects, SMART Goals, Retrospective Planning Game
-
Question 6 of 20
6. Question
In agile, the kaizen approach involves:
Correct
Congratulations!
Incorrect
The correct answer is C. Small, incremental improvements by the people who are doing the work
-
Question 7 of 20
7. Question
You have been asked to review an agile team’s recently enhanced methodology to assess its effectiveness. The desirable characteristics that you should be looking for include:
Correct
Congratulations!
Incorrect
The correct answer is D. A preference for face-to-face communications, not too much process weight, recommendations for larger teams to use heavier methods
-
Question 8 of 20
8. Question
The characteristics of SMART goals are:
Correct
Congratulations!
Incorrect
The correct answer is D. Specific, Measurable, Attainable, Relevant, Timely
-
Question 9 of 20
9. Question
Continuous improvement is a core benefit of which agile practices?
Correct
Congratulations!
Incorrect
The correct answer is C. Pair programming, daily stand-up meetings, retrospectives
-
Question 10 of 20
10. Question
When considering process tailoring, it is useful to keep in mind that the XP core practices are:
Correct
Congratulations!
Incorrect
The correct answer is D. Balanced
-
Question 11 of 20
11. Question
Which of the following is not one of the questions that we are continually asking in a product feedback loop?
Correct
Congratulations!
Incorrect
The correct answer is D. Did the project get shipped?
-
Question 12 of 20
12. Question
The primary reason for doing a project pre-mortem is to:
Correct
Congratulations!
Incorrect
The correct answer is C. Identify potential risk so that we can mitigate them.
-
Question 13 of 20
13. Question
You are analyzing a process and are on the lookout for the anti-patterns of poor methodologies. What characteristics should you be looking for?
Correct
Congratulations!
Incorrect
The correct answer is C. One-size-fits-all, intolerant, heavy, embellished
-
Question 14 of 20
14. Question
On the chart used in the Timeline exercise for gathering data in a retrospective, a horizontal line can be added below the x-axis to represent:
Correct
Congratulations!
Incorrect
The correct answer is B. Team emotional responses over time
-
Question 15 of 20
15. Question
Process tailoring is best undertaken on agile projects when:
Correct
Congratulations!
Incorrect
The correct answer is B. Experienced practitioners want to address an issue.
-
Question 16 of 20
16. Question
Which of the following benefits would an agile team most likely gain from performing a self-assessment?
Correct
Congratulations!
Incorrect
The correct answer is A. Improve the team’s practices.
-
Question 17 of 20
17. Question
When undertaking process analysis, what are the success criteria that characterize a useful methodology?
Correct
Congratulations!
Incorrect
The correct answer is B. The project got shipped, leadership remained intact, and the team would work the same way again.
-
Question 18 of 20
18. Question
When should agile teams collect lessons learned?
Correct
Congratulations!
Incorrect
The correct answer is B. Throughout the project
-
Question 19 of 20
19. Question
Your sponsor is asking about tailoring the company’s newly adopted agile methodology. Your advice should be:
Correct
Congratulations!
Incorrect
The correct answer is D. We should try it first, then consider tailoring it.
-
Question 20 of 20
20. Question
Teams gain the most benefits from using an agile approach in:
Correct
Congratulations!
Incorrect
The correct answer is C. Projects with medium levels of complexity in both technology and requirements
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
You must specify a text. |
08_Test Agile – General
Ai 20 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 08_Test Agile - General
Mulțumim pentru participarea la testul 08_Test Agile - General. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
While there is value in using processes and tools, the Agile Manifesto encourages us to value more:
Correct
Congratulations!
Incorrect
The correct answer is A – Individuals and interactions
-
Question 2 of 20
2. Question
In the Agile Manifesto, what is valued more than following a plan?
Correct
Congratulations!
Incorrect
The correct answer is D – Responding to change
-
Question 3 of 20
3. Question
What are the three pillars of Scrum?
Correct
Congratulations!
Incorrect
The correct answer is B – Transparency, Inspection, Adaptation
-
Question 4 of 20
4. Question
Which of the statements below correctly describe a ‘persona’?
Correct
Congratulation!
Incorrect
The correct answer is A – Personas are detailed, synthetic biographies of fictitious users of the future product
-
Question 5 of 20
5. Question
The comprehensive checklist of necessary activities that ensure that only truly done features are delivered is called:
Correct
Congratulations!
Incorrect
The correct answer is C – Definition of Done
-
Question 6 of 20
6. Question
Which of the following statement best describes the role of a Product Owner:
Correct
Congratulations!
Incorrect
The correct answer is A – Main stakeholder accountable for setting priorities for the project team and defining the product features to deliver the maximum business value.