01_Test PMP® General
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 01_Test PMP® General
Mulțumim pentru participarea la testul 01_Test PMP® General. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Three items from the issue log have been assigned to a team member. However, no action has been taken by the agreed-upon due date. After three calls to the team member, the work is finally completed. Which of the following is the BEST preventive action to take NOW?
Correct
Congratulations!
Incorrect
The correct answer is B. Notice that there are multiple „right answers.” However, removing the team member (choice A) is too drastic. By this time, you would have built a team through team building. Removing one person might drastically change team dynamics. Though choices C and D could be done, they involve taking action without knowing the reason there was a problem. Choices C and D may not solve the problem, and the same problem could resurface. Only choice B gets to the root cause.
-
Question 2 of 10
2. Question
You have a cost plus fee contract with the customer and an arrangement with your manager whereby you will receive 10 percent of the contract amount as your payment for services. While completing the project, you discover that the actual cost will be lower than expected, thus decreasing your fee. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is B. This situation tests ethics. Choice C is gold plating and should not be done without the customer’s approval. Choice D is even worse because it provides no additional benefit to the customer. Choice A, in theory, provides benefit to the customer if the more expensive equipment provides value, but it should not be done without customer approval.
-
Question 3 of 10
3. Question
When planning risk responses, the strategy of changing the project management plan to eliminate the risk is known as:
Correct
Congratulations!
Incorrect
The correct answer is A. This is the definition of the risk response strategy of „avoidance.”
-
Question 4 of 10
4. Question
You are tracking your project using earned value management (EVM) and find you are behind schedule but under budget. Your variances show schedule variance (SV) =-50.000usd, cost variance (CV) =100.000usd, and your actual cost are 500.000usd. What are the CPI, PV and SPI?
Correct
Congratulations!
Incorrect
The correct answer is D. First find EV = CV + AC = $600. Calculate CPI = EV/AC = $600/$500 = 1.20. Next, to find PV, you would use the formula PV = EV – SV = $550. Now you can compute SPI = EV/PV = 600/550 = 1.09. In Answer A, PV is wrong and in answers B and C all three values are incorrect.
-
Question 5 of 10
5. Question
You have just learned that one of your team members has not been adequately trained to complete project activities as assigned to him. How will you handle this situation?
Correct
Congratulations!
Incorrect
The correct answer is D. Would you select a choice that said „remove the resource,” like choice A? Why? There is no need for the project manager to take such drastic action, because he would have accounted for the team member’s level of experience and productivity in the project management plan. Since training for project work is the cost of the project, choice B cannot be right. Choice C is not correct, as no impact to the project is referenced in the question. Mentoring (choice D) is the only logical choice, and work that a project manager may be frequently called on to perform.
-
Question 6 of 10
6. Question
What is the expected monetary value of the decision displayed in the chart?
Correct
Congratulations!
Incorrect
The correct answer is A. The expected monetary value is probability times impact. In this case you multiply the probabilities together and then multiply the impact. 0.20 x 0.10 x 0.20 x $1000 = $4.
-
Question 7 of 10
7. Question
What does “resource leveling” mean in project management?
Correct
Congratulations!
Incorrect
The correct answer is B. Resource leveling usually extends vs. shortens (choice A) the project. It does not necessarily require gaining outside resources (choice C) or add cost (choice D). It is a way to use existing resources more efficiently.
-
Question 8 of 10
8. Question
Originally a project had four team members. Now the scope has extended, and there are a total of six people on the project team. How many communication channels does the project have?
Correct
Congratulations!
Incorrect
The correct answer is D. The formula is [N x (N – 1)]/2. Therefore 6(5)/2 = 15. Watch for questions that ask how many MORE communication channels there are.
-
Question 9 of 10
9. Question
You just completed a cost estimate on the project, and you’re assuming there is a 15 percent chance you will exceed this estimate. You are:
Correct
Congratulations!
Incorrect
The correct answer is B. With normal distribution, the mean indicates you have a 50 percent chance of being over or under your estimate. Since you have only a 15 percent chance of being over, you are above (or to the right of) the mean.
-
Question 10 of 10
10. Question
Which motivational theory says that what motivates people is the work itself, including such things as responsibility, self-actualization, and professional growth?
Correct
Congratulations!
Incorrect
The correct answer is D. This is the essence of Herzberg’s hygiene factors.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
02_Test PMP® – Professional Responsibility
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 02_Test PMP® - Professional Responsibility
Mulțumim pentru participarea la testul 02_Test PMP® - Professional Responsibility. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
You are offered a job as project manager for a fixed cost project. At the same time, you are approached by another client to work on her project on a time and material basis at a higher hourly rate. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is A. Tell the new client that you need some time to consider all your options before giving her an answer.
-
Question 2 of 10
2. Question
As a senior leader in the project management field, you receive a voice mail from one of your competitor’s junior project managers asking for help in the project management discipline. What is the most appropriate course of action?
Correct
Congratulations!
Incorrect
The correct answer is D. Talk to your supervisor and apprise her of the situation before initiating contact.
-
Question 3 of 10
3. Question
Your project team is working with a vendor to correct some programming errors found during user acceptance testing. The decision is made to work through lunch and order take out. When the food is delivered, the vendor says that the bill has been taken care of. What do you do?
Correct
Congratulations!
Incorrect
The correct answer is D. You decline and pay for your own meal.
-
Question 4 of 10
4. Question
You work for an organization that has no rules with regard to vendor kickbacks or special gifts. A vendor approaches you with a trip to Paris, provided you help him get the contract with your organization. What would be the most prudent thing to do?
Correct
Congratulations!
Incorrect
The correct answer is C. Decline the offer and advise the vendor on the standard bidding process.
-
Question 5 of 10
5. Question
You are responsible for developing a cost estimate to bid on a government contract. The scope was set by the government. Your supervisor says the cost estimate is too expensive and should be reduced by one-third to assure your company wins the contract. Your analysis shows that any reduction to the proposed cost estimate will make the project unable to meet the specified scope. What do you do?
Correct
Congratulations!
Incorrect
The correct answer is C. Explain to your supervisor in writing that your analysis shows a reduction in the cost estimate will make the project unable to meet the specified scope.
-
Question 6 of 10
6. Question
You are the project manager for one part of a new program in your organization. You are four months into a three year project when your project team makes significant discoveries on the project. What is the BEST thing to do?
Correct
Congratulations!
Incorrect
The correct answer is D. Make certain you tell the other project managers involved in this program about the discoveries at the weekly meeting.
-
Question 7 of 10
7. Question
Which of the following would BEST prevent cultural problem on your international project?
Correct
Congratulations!
Incorrect
The correct answer is C. Training in cultural differences between the other countries
-
Question 8 of 10
8. Question
You are reviewing the expense report for one of your team members when you notice a payment he made in another country. You think this payment is a bribe. What is your first course of action?
Correct
Congratulations!
Incorrect
The correct answer is A. Seek legal advice
-
Question 9 of 10
9. Question
Your best programmer is an independent contractor. Recently, you learned that she is working on a project in the evening of one of your competitors. Your BEST course of action is to:
Correct
Congratulations!
Incorrect
The correct answer is B. Get her sign a non-disclosure agreement
-
Question 10 of 10
10. Question
My third-party supplier does not meet his deadlines. He’s the friend of a senior manager and ignores me as the project manager. How should I deal with this?
Correct
Congratulations!
Incorrect
The correct answer is B. Construct a better procurement process for next time.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
03_Test PMP® – PM Framework
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 03_Test PMP® - PM Framework
Mulțumim pentru participarea la testul 03_Test PMP® - PM Framework. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Michael wants to help project managers from your organization to understand the project management life cycle. Many of them are confusing the project life cycle with the project management life cycle. Which of the following identifies the difference between these two life cycles?
Correct
Congratulations!
Incorrect
The correct answer is D. The project life cycle describes what you need to do to complete the work
-
Question 2 of 10
2. Question
The CIO and the head of marketing of a drug development services organization privately discuss a change to a key task in the design phase of a project. After the discussion, they tell the project manager to make the appropriate changes. This scenario is an example of:
Correct
Congratulations!
Incorrect
The correct answer is D. A project coordinator role
-
Question 3 of 10
3. Question
Who is responsible for determining the appropriate life cycle for a specific project?
Correct
Congratulations!
Incorrect
The correct answer is C. Project manager/project management team
-
Question 4 of 10
4. Question
All of the following statements about the level of authority of the project manager are true EXCEPT:
Correct
Congratulations!
Incorrect
The correct answer is D. Authority of the project manager is limited in a strong matrix organization.
-
Question 5 of 10
5. Question
A frequent complaint about matrix organization is that communications are:
Correct
Congratulations!
Incorrect
The correct answer is C. Complex
-
Question 6 of 10
6. Question
A project may end for all of the following reasons EXCEPT:
Correct
Congratulations!
Incorrect
The correct answer is B. The project manager has left the company.
-
Question 7 of 10
7. Question
Your management has decided that all orders will be treated as „projects” and that project managers will be used to update orders daily, resolving issues and ensuring that the customer formally accepts the product within 30 days of completion. The revenue from the individual orders can vary from US $300 to US $300,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?
Correct
Congratulations!
Incorrect
The correct answer is C. This is a recurring process.
-
Question 8 of 10
8. Question
Which of the following best describes the role of the project manager?
Correct
Congratulations!
Incorrect
The correct answer is B. Leading the project team to meet the project objectives
-
Question 9 of 10
9. Question
Which of the following are the most resistant to change?
Correct
Congratulations!
Incorrect
The correct answer is C. People
-
Question 10 of 10
10. Question
Your customer has asked for a 2,000-call capacity for the new call center project. However, one of your company’s technical experts believes a 3,000-call capacity can be reached. Another thinks that based on the technical needs of the customer, the capacity needs to be only 1,500-calls. What is the best thing to do?
Correct
Congratulations!
Incorrect
The correct answer is A. Meet with the customer to better understand the reasons behind the 2,000-call capacity.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
04_Test PMP® – Integration Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 04_Test PMP® - Integration Management
Mulțumim pentru participarea la testul 04_Test PMP® - Integration Management. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
The lessons learned register:
Correct
Congratulations!
Incorrect
The correct answer is B. Should be created early in the project and updated as the project progresses
-
Question 2 of 10
2. Question
Reviewing the initiating processes at the beginning of each phase:
Correct
Congratulations!
Incorrect
The correct answer is B. Helps to keep the project focused on the business need that the project was undertaken to address.
-
Question 3 of 10
3. Question
An activity needs more time because an identified risk has occurred. The project manager determines that there is enough reserve to accommodate the change. Who needs to approve the change?
Correct
Congratulations!
Incorrect
The correct answer is B. Project Manager
-
Question 4 of 10
4. Question
You are a new project manager who has never managed a project before and you have been asked to plan a new project. It would be BEST in this situation to rely on _______ during planning to improve your chance of success.
Correct
Congratulations!
Incorrect
The correct answer is D. historical information
-
Question 5 of 10
5. Question
___________ are factors that will strongly limit the project management team’s options.
Correct
Congratulations!
Incorrect
The correct answer is A. Organizational policies
-
Question 6 of 10
6. Question
Which of the following BEST describes a project management plan?
Correct
Congratulations!
Incorrect
The correct answer is C. Formal, approved document used to manage and control the project
-
Question 7 of 10
7. Question
Who has the ultimate responsibility for approving change requests?
Correct
Congratulations!
Incorrect
The correct answer is D. The individuals identified in the project management plan
-
Question 8 of 10
8. Question
You have created the project charter but could not get it approved. Your manager and other managers have asked you that the project must begin immediately. Which is the BEST thing to do?
Correct
Congratulations!
Incorrect
The correct answer A. Show your manager the impact of proceeding without approval
-
Question 9 of 10
9. Question
Who applies project selection methods to decide whether to accept or reject a project?
Correct
Congratulations!
Incorrect
The correct answer A. The project sponsor
-
Question 10 of 10
10. Question
You have just been assigned to take over a project that your management has told you is “out of control”. When you asked your management what the problems were, they had no specifics, but said that the project was behind schedule, over budget and the client was dissatisfied. Which of the following should be of the most concern to you?
Correct
Congratulations!
Incorrect
The correct answer is B. There is very little documentation related to the project
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
05_Test PMP® – Scope Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 05_Test PMP® - Scope Management
Mulțumim pentru participarea la testul 05_Test PMP® - Scope Management. Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Which of the following is an output of the Collect Requirements process?
Correct
Congratulations!
Incorrect
The correct answer is A. Requirements traceability matrix
-
Question 2 of 10
2. Question
When we build a WBS, we make a:
Correct
Congratulations!
Incorrect
The correct answer is D. Decomposition
-
Question 3 of 10
3. Question
As project manager, you are about to start the Define Scope process. You have the project charter and the organizational process assets list. What else do you need before you begin?
Correct
Congratulations!
Incorrect
The correct answer is B. Requirements documentation
-
Question 4 of 10
4. Question
You have a signed project charter and are in the process of creating a project scope statement. You have asked the team for input to ensure that the project scope statement is complete. However, the team is struggling with defining the scope. Which of the following BEST describes the problem?
Correct
Congratulations!
Incorrect
The correct answer is B. The team is working on the project scope statement without the benefit of organizational process assets
-
Question 5 of 10
5. Question
An organization is starting a PMO. For the initial phase, the PMO director has decided to roll out the use of project charters. As a project manager, why would you be encouraged by this plan?
Correct
Congratulations!
Incorrect
The correct answer is C. The project charter authorizes you to use organizational resources to accomplish the objectives of the project.
-
Question 6 of 10
6. Question
The following is an example of a constraint:
Correct
Congratulations!
Incorrect
The correct answer is A. A predefined budget
-
Question 7 of 10
7. Question
One of the stakeholders on the project contacts the project manager to discuss some additional scope they would like to add to the project. The project manager asks for details in writing and then works through the control scope process. What should the project manager do NEXT when the evaluation of the requested scope is completed?
Correct
Congratulations!
Incorrect
The correct answer is B. Perform integrate change control
-
Question 8 of 10
8. Question
The following is true about the WBS:
Correct
Congratulations!
Incorrect
The correct answer is B. Each descending level of the WBS represents an increasingly detailed definition of the project work.
-
Question 9 of 10
9. Question
An output of Define Scope is:
Correct
Congratulations!
Incorrect
The correct answer is C. Project scope statement.
-
Question 10 of 10
10. Question
All of the following are true about the project scope statements EXCEPT:
Correct
Congratulations!
Incorrect
The correct answer is A. It is an output of Validate Scope process.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
06_Test PMP® – Schedule Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 06_Test PMP® - Schedule Management
Mulțumim pentru participarea la testul 06_Test PMP® - Schedule Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:
Correct
Congratulations!
Incorrect
The correct answer is A. Crashing.
-
Question 2 of 10
2. Question
In rolling wave planning:
Correct
Congratulations!
Incorrect
The correct answer is B. The work to be accomplished in the near term is planned in detail at a low level of WBS.
-
Question 3 of 10
3. Question
You are examining the network paths for your project. Path A’s duration is: 1 – 4 – 3 – 5 – 8; Path B’s duration is 1 – 3 – 5 – 6 – 7; Path C’s duration is 1 – 4 – 5 – 4 – 10; and Path D’s duration is 4 – 3 – 4 – 4 – 8. Which of the following is the critical path for this project?
Correct
Congratulations!
Incorrect
The correct answer is B. Path C
-
Question 4 of 10
4. Question
In what way does free float differ from total float?
Correct
Congratulations!
Incorrect
The correct answer is C. Free float is the amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities, whereas total float is concerned with delays that do not affect the project finish date.
-
Question 5 of 10
5. Question
The “fast-tracking” method of schedule compression involves:
Correct
Congratulations!
Incorrect
The correct answer is B. Performing activities in parallel, thereby increasing risk.
-
Question 6 of 10
6. Question
The amount of time that an activity may be delayed without affecting its successor is:
Correct
Congratulations!
Incorrect
The correct answer is C. Free float
-
Question 7 of 10
7. Question
A team member makes a change to a software project without letting anyone else know. She assures you that it did not affect the schedule, and it significantly enhances the product. What should the project manager do FIRST?
Correct
Congratulations!
Incorrect
The correct answer is C. Review the change to understand how it affects scope, budget, schedule, quality and risk.
-
Question 8 of 10
8. Question
Diana is the project manager for the ALPHA construction project. Her foreman informs her that, due to the humidity, the concrete will need to cure for an additional 24 hours before the framing can begin. To accommodate, Diana adds _____________time to the framing activity.
Correct
Congratulations!
Incorrect
The correct answer is B. Lag
-
Question 9 of 10
9. Question
You have designed an improved system for a consumer product that could decrease repair cost for consumer. Management is impressed with your idea, but has decided to wait until next year to implement it. What is the BEST thing to do?
Correct
Congratulations!
Incorrect
The correct answer is B. Wait until next year
-
Question 10 of 10
10. Question
Which statement best describes the proper way to develop the initial project schedule?
Correct
Congratulations!
Incorrect
The correct answer is D. Find an MS Project file with a proven WBS and activity list template, review the estimated duration and resource assignments for each activity, and review the logical dependencies between the activities and work packages.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
07_Test PMP® – Cost Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 07_Test PMP® - Cost Management
Mulțumim pentru participarea la testul 07_Test PMP® - Cost Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
The project manager is working on a high profile project where there is a huge demand to complete the project within the budget. The project manager is new, but well trained and is excited to see that the project is spending less than budgeted. As a result, the project manager was planning to take a holiday when a more senior project manager warned him that he has some important work to do on the project. Why would the senior project manager give such warning on this project?
Correct
Congratulations!
Incorrect
The correct answer is A. Under budget could mean that work that was scheduled to be done has not been completed. The project manager should look at how the cost performance compares to the schedule performance
-
Question 2 of 10
2. Question
If planned value (PV) is $29.000, actual cost (AC) is $32.000, and earned value (EV) is $30.000, what is the schedule variance (SV)?
Correct
Congratulations!
Incorrect
The correct answer is B. $1.000
-
Question 3 of 10
3. Question
Given: BAC=200, AC= 120, EV=80, CPI=0,666. Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is:
Correct
Congratulations!
Incorrect
The correct answer is D. 240.
-
Question 4 of 10
4. Question
Given the following information, which item is the MOST over budget?
Item 1: PV = 10,000; AC = 11,000; EV = 10,000
Item2: PV = 9,000; AC = 8,000; EV = 7,000
Item 3: PV = 8,000; AC = 8,000; EV = 8,000
Item 4: PV = 7,000; AC = 7,000; EV = 5,000
Correct
Congratulations!
Incorrect
The correct answer is D. Item 4.
-
Question 5 of 10
5. Question
You have spent $555.555 on your project to date. The program manager wants to know why costs have been running so high. You explain that the resource cost has been greater than expected and should level out over the next six months. What does $555.555 represent to the program manager?
Correct
Congratulations!
Incorrect
The correct answer is B. Actual cost.
-
Question 6 of 10
6. Question
If a project has a CPI of 1.05 and an SPI of 1.01, this indicates:
Correct
Congratulations!
Incorrect
The correct answer is D. The project is progressing faster and costing less than planned.
-
Question 7 of 10
7. Question
If project A has a Net Present Value (NPV) of US $30,000 and project B has an NPV of US $50,000, what is the opportunity cost if project B is selected?
Correct
Congratulations!
Incorrect
The correct answer is B. $30,000
-
Question 8 of 10
8. Question
You are in the middle of a new product development project for your publicly traded company when you discover that the previous project manager made a US $3,000,000 payment that was not approved in accordance with your company policies. Luckily, the project CPI is 1.2. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is B. Contact your manager
-
Question 9 of 10
9. Question
You are trying to decide whether to lease or buy an item for your project. The daily lease cost is $150. To purchase the item, the investment cost is $2,000 and the daily cost is $50. In how many days will the lease cost be the same as the purchase cost?
Correct
Congratulations!
Incorrect
The correct answer is C. 20
-
Question 10 of 10
10. Question
Although several factors should be considered when developing estimates, the primary basis for estimating time and cost for an activity is … .
Correct
Congratulations!
Incorrect
The correct answer is A. resource usage and productivity rates
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
08_Test PMP® – Quality Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 08_Test PMP® - Quality Management
Mulțumim pentru participarea la testul 08_Test PMP® - Quality Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
While testing the strength of concrete poured on your project, you discover that over 35% of the concrete does not meet your company’s quality standards. You feel certain the concrete will function as it is, and you don’t think the concrete needs to meet the quality level specified. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is D. Report the lesser quality level and try to find a solution.
-
Question 2 of 10
2. Question
What does cost of quality mean?
Correct
Congratulations!
Incorrect
The correct answer is C. Determining the costs incurred to ensure quality.
-
Question 3 of 10
3. Question
If a process has a lack of consistency and predictability it is said to be:
Correct
Congratulations!
Incorrect
The correct answer is A. Out of control
-
Question 4 of 10
4. Question
You are a project manager with limited resources on the project. Several quality defects have been discovered, causing the stakeholders concern. You wish to begin by attacking the causes that have the highest number of defects associated with them. Which tool shows defects by volume from greatest to least?
Correct
Congratulations!
Incorrect
The correct answer is A. Pareto chart.
-
Question 5 of 10
5. Question
Which of the following is NOT an output of the Control Quality process?
Correct
Congratulations!
Incorrect
The correct answer is B. Quality audits
-
Question 6 of 10
6. Question
Testing the entire population would:
Correct
Congratulations!
Incorrect
The correct answer is A. Take too long
-
Question 7 of 10
7. Question
If two events cannot occur in a single trial, they are:
Correct
Congratulations!
Incorrect
The correct answer is B. mutually exclusive
-
Question 8 of 10
8. Question
You are the project manager of a new facility construction project. The structural steel is in place, and the heating pipes are going into place when the senior management informs you that he is worried that the project will not meet the quality standards. What should you do in this situation?
Correct
Congratulations!
Incorrect
The correct answer is C. Gather the quality assurance team
-
Question 9 of 10
9. Question
During project executing a project team member informs the project manager that based on her observation the project cannot meet the quality standards set for it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in?
Correct
Congratulations!
Incorrect
The correct answer is A. Manage Quality
-
Question 10 of 10
10. Question
Who of the following has primary responsibility for establishing design and test specifications?
Correct
Congratulations!
Incorrect
The correct answer is C. Engineering
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
09_Test PMP® – Resource Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 09_Test PMP® - Resource Management
Mulțumim pentru participarea la testul 09_Test PMP® - Resource Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Maslow’s hierarchy of needs talks about how people need to satisfy various personal needs. What is the correct sequence for those needs?
Correct
Congratulations!
Incorrect
The correct answer is D.Physiological, safety, love, esteem and self-actualization
-
Question 2 of 10
2. Question
My team is confused. We see terms that appear to be interchangeable, but other teams treat them as though they have specific, unique meanings. How can we find out what the terms mean?
Correct
Congratulations!
Incorrect
The correct answer is C. There is no one source that defines every project management term, but the PMBOK® Guide glossary is a great resource for accurate definitions of many of them.
-
Question 3 of 10
3. Question
The Acquire Resources process:
Correct
Congratulations!
Incorrect
The correct answer is C. Is performed throughout the project as needed
-
Question 4 of 10
4. Question
ABC, a matrix organization of which a project manager’s project team is a part, has a policy of no bonus for project work. The project manager’s current project has an aggressive timeline and a difficult technical obstacle to overcome. A new product offering is dependent on this project’s success in the current timeline. The project manager has heard grumbling from his team about the fact that they cannot be rewarded for their effort. What is the FIRST thing the project manager should do?
Correct
Congratulations!
Incorrect
The correct answer is D. The project manager should talk with the team about the importance of getting this done on time and explain the company policy.
-
Question 5 of 10
5. Question
The Resource Breakdown Structure:
Correct
Congratulations!
Incorrect
The correct answer is D. is a hierarchical representation of resources by category and type
-
Question 6 of 10
6. Question
Which document is best suited for tracking the assignment of team members to specific task?
Correct
Congratulations!
Incorrect
The correct answer is D. RACI Matrix
-
Question 7 of 10
7. Question
I know that people skills are essential for a project manager to communicate and execute a project successfully. How can I manage all types of team members when we are so different in the ways we communicate?
Correct
Congratulations!
Incorrect
The correct answer is D. Notice how others choose to communicate and adapt your style to consider theirs.
-
Question 8 of 10
8. Question
Co-location can help with:
Correct
Congratulations!
Incorrect
The correct answer is B. Building the team
-
Question 9 of 10
9. Question
A project manager had a complex problem to solve and made a decision about what needed to be done. A few months later, the problem resurfaced. What did the project manager MOST likely not do?
Correct
Congratulations!
Incorrect
The correct answer is B. Confirm that the decision solved the problem
-
Question 10 of 10
10. Question
The project has been challenging to manage. Everyone has been on edge to complete the project on time. Unfortunately, the tension has grown to the point where team meetings have become shouting matches and little work is accomplished during the meetings. One team member asks to be excused from future team meetings, as all the shouting upsets him. Meanwhile, the sponsor has asked to attend team meetings in order to better understand how the project is going and the issues involved in completing the project, and the customer has started discussions about adding scope to the project. In this situation, it would be BEST for the project manager to:
Correct
Congratulations!
Incorrect
The correct answer is C. Create new ground rules for the meetings and introduce them to the team.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
10_Test PMP® – Communications Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 10_Test PMP® - Communications Management
Mulțumim pentru participarea la testul 10_Test PMP® - Communications Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
How many communication channels will be required in a project in which 30 individual are participating?
Correct
Congratulations!
Incorrect
The correct answer is D. 435
-
Question 2 of 10
2. Question
The level of detail of work performance reports is described in the:
Correct
Congratulations!
Incorrect
The correct answer is B. Communications management plan
-
Question 3 of 10
3. Question
Who has the ultimate responsibility for making sure that a message in the project team is understood?
Correct
Congratulations!
Incorrect
The correct answer is B. The sender
-
Question 4 of 10
4. Question
How much time should a project manager spend in communication activities?
Correct
Congratulations!
Incorrect
The correct answer is D. 70%–90%
-
Question 5 of 10
5. Question
You are in charge of a project that is going to miss the milestones that were set at the enterprise level by 2 weeks. What do you do?
Correct
Congratulations!
Incorrect
The correct answer is A. Advise management of the revised project plan and timeline.
-
Question 6 of 10
6. Question
A good project manager tends to ______ above all else when it comes to active communications.
Correct
Congratulations!
Incorrect
The correct answer is C. Listen
-
Question 7 of 10
7. Question
You are in a project status meeting, and the situation is not good. Everyone is talking at the same time, there are people who are not participating and many topics are being discussed at random. Which of the following rules for effective meetings is NOT being adhered to?
Correct
Congratulations!
Incorrect
The correct answer is D. Create and publish an agenda
-
Question 8 of 10
8. Question
You are talking with a team member. Communications are often enhanced when the sender ___ the receiver.
Correct
Congratulations!
Incorrect
The correct answer is D. Shows concern for the perspective of
-
Question 9 of 10
9. Question
You are a project manager for a US $3,000,000 product development project. Your project is well into the execution phase and remains on time, on budget and on specification. This morning, your project sponsor called to express concern about the project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mail is too impersonal and verbal updates are preferred. This situation suggests problems with which of the following project management processes?
Correct
Congratulations!
Incorrect
The correct answer is C. Monitor Communications
-
Question 10 of 10
10. Question
Which of the following approaches does NOT describe a proper way to effectively communicate with the project stakeholders?
Correct
Congratulations!
Incorrect
The correct answer is A. Invite them to lunch once per month and pay for the lunch
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
11_Test PMP® – Risk Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 11_Test PMP® - Risk Management
Mulțumim pentru participarea la testul 11_Test PMP® - Risk Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
Which one of these is NOT a typical way to deal with threats?
Correct
Congratulations!
Incorrect
The correct answer is D. Share
-
Question 2 of 10
2. Question
A construction project has a work package that could result in fatalities or long terms disabilities with losses over US 2.2 million. The company has had a clean record in the past and has won several safety awards. An appropriate risk response strategy is to:
Correct
Congratulations!
Incorrect
The correct answer is D. Not do the work package.
-
Question 3 of 10
3. Question
A project is facing the following risks: 20 percent chance a part is not available, creating an additional fee of US 30.000; 10 percent chance the team requires additional training for a cost of US 12.000; 25 percent chance the second planned quality test costing US 8000 is unnecessary. What is the expected monetary value of these risks?
Correct
Congratulations!
Incorrect
The correct answer is B. US -5,200
-
Question 4 of 10
4. Question
What risk management process MOST affects the project management plan?
Correct
Congratulations!
Incorrect
The correct answer is C. Plan Risk Responses
-
Question 5 of 10
5. Question
Which risk response strategy does NOT imply further monitoring actions by the project team?
Correct
Congratulations!
Incorrect
The correct answer is A. Escalate
-
Question 6 of 10
6. Question
A project has had some problems, but now seems under control. In the last few months almost all the reserve has been used up and most of the negative impacts of events that had been predicted have occurred. There are only four activities left and two of them are on the critical path. Management now informs the project manager that it will be in the performing organization’s best interest to finish the project two weeks earlier than scheduled in order to receive an additional profit. In response, the project manager sends out a request for proposal for some work that the team was going to do in the hopes that another company might be able to do the work faster. The project manager can best be said to be attempting to work with:
Correct
Congratulations!
Incorrect
The correct answer is B. Opportunities
-
Question 7 of 10
7. Question
If a risk event has a 90 percent chance of occurring and the consequences will be U.S. $ 10,000, what does U.S. $ 9,000 represent?
Correct
Congratulations!
Incorrect
The correct answer is C. Expected monetary value
-
Question 8 of 10
8. Question
During the Identify Risks process, a project manager made a long list of risk identified with all the stakeholders using various methods. He then made sure that all risks were understood and that triggers had been identified. Later, in plan risk responses, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong?
Correct
Congratulations!
Incorrect
The correct answer is B. More people should be involved in Plan Risk Response.
-
Question 9 of 10
9. Question
Risk probability and impact assessment, and Risk data quality assessment are done during ________ process.
Correct
Congratulations!
Incorrect
The correct answer is A. Perform Qualitative Risk Analysis
-
Question 10 of 10
10. Question
A team member assigned to the project needs two day of training to satisfactorily complete certain activities. No one else with the necessary skills is available to the project team. What is the BEST thing to do?
Correct
Congratulations!
Incorrect
The correct answer is D. Include the training in the project management plan.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
12_Test PMP® – Procurement Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 12_Test PMP® - Procurement Management
Mulțumim pentru participarea la testul 12_Test PMP® - Procurement Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
All of the following are outputs of the Plan Procurement Management process, EXCEPT:
Correct
Congratulations!
Incorrect
The correct answer is C. Contract signed
-
Question 2 of 10
2. Question
The decision on whether a product or service can be produced by the project management team or can be purchased is called what?
Correct
Congratulations!
Incorrect
The correct answer is C. Make or buy analysis
-
Question 3 of 10
3. Question
With which type of contract is the seller MOST concerned about project scope?
Correct
Congratulations!
Incorrect
The correct answer is A. Fixed price
-
Question 4 of 10
4. Question
What is the main reason to make sure all contractual agreements are closed at the end of the project?
Correct
Congratulations!
Incorrect
The correct answer is C. Contracts are legally binding agreements
-
Question 5 of 10
5. Question
While completing work for your project, the seller’s subcontractor suffers a major fire. The fire destroys the heating system they were building for your project. What is the BEST thing to do?
Correct
Congratulations!
Incorrect
The correct answer is C. Be prepared to extend the deliverable due date
-
Question 6 of 10
6. Question
A seller is working on a cost reimbursable (CR) contract when the buyer decides he would like to expand the scope of services and change to a fixed price (FP). All of the following are the seller’s options EXCEPT?
Correct
Congratulations!
Incorrect
The correct answer is D. Starting over with a new contract.
-
Question 7 of 10
7. Question
A company and its seller are in the middle of a long dispute over the cost of terminating the contract. The project manager determines that the only way to resolve the problem is to have it heard and resolved by a neutral party. To accomplish this, the project manager should use a(n):
Correct
Congratulations!
Incorrect
The correct answer is C. Arbitrator
-
Question 8 of 10
8. Question
While working on your contract, you receive a claim from the seller for additional cost for the reports the team members have requested. You know that the reports are not in the contract and you were not aware that the team needed the information. What should you do?
Correct
Congratulations!
Incorrect
The correct answer is B. Pay the claim and institute better procedure
-
Question 9 of 10
9. Question
A project manager is in a middle of creating a request for proposal (RFP). What procurement process is he in?
Correct
Congratulations!
Incorrect
The correct answer is A. Plan Procurements Management
-
Question 10 of 10
10. Question
While completing work on your contract, the seller is refused access to the facility by your company’s security force. If access to the facility is stipulated in the contract, what should the project manager do?
Correct
Congratulations!
Incorrect
The correct answer is C. Work with the seller to gain access. Expect to receive a claim for additional time and cost.
Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
You must specify a text. |
13_Test PMP® – Stakeholder Management
Ai 10 întrebări similare celor din examen. O singură variantă de răspuns este corectă. Poți reveni la o întrebare dacă o bifezi pentru REVIZUIRE.
Succes!
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Test 13_Test PMP® - Stakeholder Management
Mulțumim pentru participarea la testul 13_Test PMP® - Stakeholder Management . Ai obținut 0 din 0 puncte, (0)
Durata:
Time has elapsed
Felicitări!
Categories
- Not categorized 0%
-
Participant:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
There is a stakeholder on my project who openly opposes its goals. How can I win this person over?
Correct
Congratulations!
Incorrect
The correct answer is D. Consider his/her point of view and adjust your project, if possible.
-
Question 2 of 10
2. Question
I have just been assigned an extremely large project. How do I handle the politics between all the stakeholders?
Correct
Congratulations!
Incorrect
The correct answer is D. Change your approach to be a manager of managers rather than of individual workers.
-
Question 3 of 10
3. Question
My newest project involves 25 department managers to coordinate and please. Each one has very specialized interests and doesn’t want to come to every project meeting. How do I deal with this large, opinionated stakeholder team?
Correct
Congratulations!
Incorrect
The correct answer is B. Find a way to ask only the department managers who have a primary interest in a feature or function to come to meetings regarding that item.
-
Question 4 of 10
4. Question
The ____ identifies stakeholders with a particular interest in or impact on quality.
Correct
Congratulations!
Incorrect
The correct answer is D. stakeholder register
-
Question 5 of 10
5. Question
How do you manage engagement on a project where the original sponsors change midway through the work? Do you change the scope in these cases?
Correct
Congratulations!
Incorrect
The correct answer is C. Check with the new sponsor to see if his or her business objectives for the project are the same as the original sponsor. Alter the scope if it makes practical sense to do so.
-
Question 6 of 10
6. Question
All of the followings are outputs of the Manage Stakeholder Engagement process, EXCEPT:
Correct
Congratulations!
Incorrect
The correct answer is C. Stakeholder plan
-
Question 7 of 10
7. Question
The _____ process is the process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
Correct
Congratulations!
Incorrect
The correct answer is D. Monitor Stakeholder Engagement
-
Question 8 of 10
8. Question
The engagement level that best describes a stakeholder who is aware of project and potential impacts and actively engaged in ensuring the project is a success is:
Correct
Congratulations!
Incorrect
The correct answer is D. Leading
-
Question 9 of 10
9. Question
Information regarding the detail level and format of the information to be distributed to stakeholders is included in the:
Correct
Congratulations!
Incorrect
The correct answer is D. Communications management plan
-
Question 10 of 10
10. Question
Michael is working on a software project and is now in the execution phase. He recently found out that some of the stakeholders have several concerns regarding the evolution of the project. Although they have not yet become issues, Michael has decided to talk to the stakeholders about their concerns. What Michael did is an activity of the _______ process.
Correct
Congratulations!
Incorrect
The correct answer is B. Manage Stakeholder Engagement